Waterproof LEA TurnLock Assembly with LEAGIR Gasket

Adding a sealing gasket to the LEA TurnLock series

The LEAGIR sealing gasket can be added to a Light-Duty Easy Assembly (LEA) TurnLock fastener to improve the seal between the stud head and the outer panel.

Sealing gaskets are already available for several TurnLock series, including MTH, HGR and HHS. The LEAGIR gasket provides a similar solution for the LEA series without significantly increasing the installation time.

The final level of water protection depends on the complete assembly, panel surface, gasket compression and installation quality. The finished application should therefore be tested when a specific waterproof or IP rating is required.

The LEAGIR sealing gasket

The LEAGIR is positioned beneath the head of the TurnLock stud. When the fastener is closed, the gasket is compressed against the outer panel to help prevent water from entering through the stud opening.

Gasket leagir.png - The LEAGIR sealing gasket
LEAGIR sealing gasket for LEA-series TurnLock fasteners.

Step 1: calculate the required stud length

The LEAGIR gasket has a thickness of approximately 1 mm. This additional thickness must be included when calculating the required stud grip length.

Add approximately 1 mm to the normal grip calculation for the selected LEA receptacle configuration.

Gasket leagir2.png - Step 1: calculate the required stud length
Include the approximate 1 mm gasket thickness in the grip-length calculation.
Assembly configurationGrip calculation including gasket
Basic panel assemblyG = P + 1
Assembly with 1.2 mm allowanceG = P + 1.2 + 1
Assembly using the minimum X valueG = P + F + X + 1 − 0.8
Assembly using the maximum allowanceG = P + F + X + 1 + 0.4

In these formulas, the additional 1 represents the approximate 1 mm thickness of the LEAGIR gasket. Use the formula that corresponds to the selected receptacle and panel configuration.

Step 2: prepare the required components

Before starting the installation, prepare all components required for the LEA TurnLock assembly:

  • The correctly sized LEA TurnLock stud
  • The selected clip-on or snap-in LEA receptacle
  • The plastic retaining washer specified for the assembly
  • The LEAGIR sealing gasket
Gasket leagir3.png - Step 2: prepare the required components
Prepare the stud, receptacle, retaining washer and LEAGIR gasket before installation.

Step 3: place the LEAGIR gasket on the stud

Slide the LEAGIR gasket over the stud and position it directly beneath the stud head. Ensure that the gasket lies flat and is not twisted or damaged.

Place gasket leagir 1.png - Step 3: place the LEAGIR gasket on the stud
Slide the gasket over the stud.
Place gasket leagir 2.png - Step 3: place the LEAGIR gasket on the stud
Position the gasket beneath the stud head.

Step 4: install the stud in the outer panel

  1. Insert the stud and attached LEAGIR gasket through the prepared opening in the outer panel.
  2. Make sure the gasket sits evenly between the stud head and the panel surface.
  3. Install the plastic retaining washer on the rear side of the panel to retain the stud.
Gasket leagir4.png - Step 4: install the stud in the outer panel
The gasket sits beneath the stud head while the retaining washer is installed on the opposite side of the panel.

Step 5: assemble and close the two panels

Install the LEA receptacle in the supporting panel or frame. Position the two panels together and align the stud with the receptacle.

Close the TurnLock fastener and check that the gasket is compressed evenly against the outer panel. The gasket should form a continuous seal without being pinched or pushed out from beneath the stud head.

Gasket leagir5.png - Step 5: assemble and close the two panels
Align the stud with the installed LEA receptacle.
Gasket leagir6.png - Step 5: assemble and close the two panels
Completed assembly with the gasket compressed beneath the stud head.

Important sealing checks

Check the panel surface

The sealing surface should be flat, clean and free from scratches, burrs or contamination that could create a leak path beneath the gasket.

Confirm the stud length

A stud that is too short may not engage correctly. A stud that is too long may not provide enough gasket compression.

Inspect the gasket

Do not install a gasket that is torn, permanently deformed or incorrectly positioned beneath the stud head.

Test the finished assembly

Perform an appropriate water-ingress test when the application must meet a defined waterproof or IP protection requirement.

Conclusion

The LEAGIR gasket provides a quick way to improve water sealing in a Light-Duty Easy Assembly TurnLock installation while retaining the fast, tool-free installation advantages of the LEA series.